Guard House Security Manager Mr. Rahim 019-3055577 / Security Supervisor Mr. Ah Peng 011-21123534
New Security SOP being enforced. We have 2 Security Personnel on duty compared to only 1 before this.
June '25
An initiative by your Ara Comm.
Trimming of Trees along Jln Ara SD 7/3
May '25
Reported to MBPJ by Mr. Gerard Philips
Cleaning up of Main guardhouse
April '25
An initiative by Mr. Stephen Tey, Mr. Asok Raghavan & Mr. Gerard Philips
After Cleaning Up..... ✨
CCTVS in the Exit Guardhouse (Post B) & the Guardhouse next to the tadika ( Post C) were all not functioning and totally disabled.
Dismantled the faulty CCTV system, repaired, refurbished and managed to get it working again....
*Stephen donated a CCTV monitor and Gerard a CCTV DVR recorder.
March '25
An initiative by Mr. Stephen Tey & Mr. Gerard Philips
After Completion......🤗
Finally, we are being monitored & safe again......
*We saved RM 7 K+ ( Quotation received to repair & replace systems )
Items donated by Mr. Stephen to be placed in Guardhouse,
Fridge
Cupboard
Radio player
Table/side table
Sun shade
March /April '25
Soil erosion on slope next to Jalan Ara 7/3.
Water flows down the slope when it rains causing major soil erosion on the slope as well as the surrounding trees. Tree roots can be seen.
Reported to MBPJ and action was taken after much persuasion by the Comm.
April '25
Reported to MBPJ by Mr. Gerard Philips
After Completion...
Visuals of work being done by MBPJ to repair the slope.
Cleaning Up of Shed along Jalan Ara 7/3
April '25
An initiative by the Ara Comm & Security Team
NO Entry sign ⛔ installed at Exit Guardhouse as Vehicles were trying to come in from the opposite direction.
April '25
An initiative by Mr. Gerard Philips
Visuals of area surrounding Our Children's playground along Jalan Ara 7/3 & 7/2
May '25
MBPJ clearing the area after a report was lodged.....
May '25
Reported to MBPJ by Mr. Gerard Philips
Installation of CCTV camera along main guardhouse railing to kick off new Security screening for Visitors starting June 1st 2025
(Refer to "New Security SOP" in Security page)
After Completion of CCTV camera installation.
May '25
An initiative by Mr. Gerard Philips
Reported to MBPJ to clean up Children's playground amenities.
*Waiting for a response from MBPJ. Will update when attended to.
May '25
Reported to MBPJ by Mr. Gerard Philips
Barrier Gate Arm at Exit Guard house broken ..(Before repairs)
Barrier gate Arm being repaired
and after repairs. Saved RM 600
(Quotation received to replace Arm RM 600)
June '25
An Initiative by Mr. Gerard Philips
Taman at ARA SD7/3 is nicely done up. New replacement by MBPJ.
Dear Ara Residents,
We are very excited to announce the launch of our new website.
(1) Safety cones - 10 numbers
(2) Vest blazers - 10 numbers
(3) Raincoats - 5 numbers
(4) LED Torch lights - 3 numbers
(5) CHOTA - 4 numbers
Thank you to BSDRA Security SubCommittee 2020/2021
Ragu Chairman
Alasri Secretary
Tan Choong Yee
Dr Jasmi Hafiz
Lee Kim Seong
Committee Members
Dear Fellow Ara Residents,
"Aduan" reports to be submitted to MBPJ
1. Potholes & Damaged Roads in ARA Sector
2. Playgrounds in ARA Sector
As promised, please find attached below 2 files on the above 2 reports on the status of our roads/potholes and the 3 Parks, which I shall submit to MBPJ for your kind reference. Kindly peruse and advise me if I may have missed out anything. I shall then call you and include if appropriate.
Warm regards.
SATU ARAH UNTUK ARA
Cheah
Chairman
27Jan2021.
MBPJ repairing SD7/5A
MBPJ repairing SD7/5A